December 19, 2025

Project Update – JoeAnna’s House Expansion

This past week, site progress included backfilling the foundation and installing radon rock beneath the slab. We formed and poured footings for the wheelchair ramps, posts, and exit stairs, and built the walls for the ramps. We installed the vapour barrier and rebar for the interior slab, which has now been poured. This week, we’ll begin framing the first floor of the addition and keep the momentum going to the holiday break. Exciting milestones ahead for JoeAnna’s House!